| Entire area of the Lubmin/Rubenow site | ~ 420 ha |
| Renting out of objects to outsourced companies | since 1991 |
| Site redevelopment supported by external employees (organized and financed by employment office) | since 1998 |
| Release of leased industrial properties for sale | 1998 |
| Sales of properties to build up two gas power plants | 1998 |
| Completion of the harbour basin and the outlet channel | 2003 |
| Confirmation of the B-Plan-Area "Lubminer Heide" | 2004 |
| Start of preparatory works for the reuse of the turbine hall by other companies | 2006 |
| Formal opening of the harbour / starting the reconstruction works in the turbine hall | 2006 |
| Completion of the road for heavy load transports from the turbine hall to the harbour | 2007 |
| Formal opening of new production plants | 2007 |